Have got the flat bar chopped up into 112mm lengths and made up a drilling jig to make the holes in the pieces.
![]() |
| Lots of flat bar pieces |
![]() |
| Drilling jig for making sure holes are in the right place |
![]() |
| The stack for one track |
Cut out the jig for welding the plates to the chain and started welding. each track is using 80 pieces of flat bar, these are not light tracks :)
![]() |
| Jig to hold flat bar in correct place for chain to be welded to each link |
![]() |
| Nate Sitting next to one complete track, 3.08mtrs (10foot) |
![]() |
| One track rolled up ready for storage |
Now to make the other one :)
Tuesday, 30 April 2013
Have finally received the two 3mtr lengths of 2060 chain for the tracks on the tank
Have started cutting the pieces to make up the main drive hubs for the tracks
![]() |
| Main drive gear cut from 10mm Mild Steel, the smaller plates will be threaded and will sandwich the hubs together |
![]() |
| Inside and outside track sprockets cut from 6mm, these are more for show as the main drive gear will be doing all the work |
Saturday, 23 March 2013
Finalised the suspension design and cut the first unit to confirm it working as required.
Am using a much larger spring in this version so that it is able to hold even more.
![]() |
| Version 1 and 2 |
![]() |
| Fresh of the machine as they are cut, very little wastage of 10mm Aluminium |
![]() |
| Parts broken out, only a very small amount of filling on the tabs that held it all together while cutting |
![]() |
| All parts ready for assembly, the spring is one of 3 cut from one bigger spring, the steel shaft is just for testing the unit, these will be spun on a lathe with a thread on the end as well |